Solis error codes explained
What 66 Solis inverter fault and error codes mean, in plain English, with safe checks you can do and when to call a licensed electrician.
Safety first: never open the switchboard, remove covers, or pull apart or disconnect the inverter, batteries, isolators or wiring. Only use the switches and buttons described here. Anything else must be done by a licensed electrician. Call 1300 209 503 or book a service request.
| Code | Message & meaning |
|---|---|
| OffFault |
OffControl device to shutdown What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| LmtByEPMFault |
LmtByEPMThe device's output is under controlled What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| LmtByDRMFault |
LmtByDRMDRM Function ON What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| LmtByTempWarning |
LmtByTempOver temperature power limited What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| LmtByFreqWarning |
LmtByFreqFrequency power limited What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| LmtByVgFault |
LmtByVgThe device is in the Volt-Watt mode What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| LmtByVarFault |
LmtByVarThe device is in the Volt-Var mode of operation What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| LmtByUnFrWarning |
LmtByUnFrUnder frequency limit What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| StandbyFault |
StandbyBypass run What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| StandbySynochWarning |
StandbySynochOff grid status to On grid status What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| GridToLoadFault |
GridToLoadGrid to load What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| Surge AlarmFault |
Surge AlarmOn-site grid surge What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| OV-G-V01Warning |
OV-G-V01Grid voltage exceeds the upper voltage range What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| UN-G-V01Warning |
UN-G-V01Grid voltage exceeds the lower voltage range What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| OV-G-F01Warning |
OV-G-F01Grid frequency exceeds the upper frequency range What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| UN-G-F01Warning |
UN-G-F01Grid frequency exceeds the lower frequency range What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| G-PHASEWarning |
G-PHASEUnbalanced grid voltage What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| G-F-GLUWarning |
G-F-GLUGrid voltage frequency fluctuation What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| NO-GridInfo |
NO-GridNo grid What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| OV-G-V02Warning |
OV-G-V02Grid transient overvoltage What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| OV-G-V03Warning |
OV-G-V03Grid transient overvoltage What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| IGFOL-FFault |
IGFOL-FGrid current tracking failure What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| OV-G-V05Warning |
OV-G-V05Grid voltage RMS instanta- neous overvoltage fault What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| OV-G-V04Warning |
OV-G-V04Grid voltage exceeds the upper voltage range What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| UN-G-V02Warning |
UN-G-V02Grid voltage exceeds the lower voltage range What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| OV-G-F02Warning |
OV-G-F02Grid frequency exceeds the upper frequency range What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| UN-G-F02Warning |
UN-G-F02Grid frequency exceeds the lower frequency range What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| NO-BatteryFault |
NO-BatteryBattery is not connected What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| OV-VbackupWarning |
OV-VbackupInverting overvoltage What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| Over-LoadWarning |
Over-LoadLoad overload fault What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| BatName-FAILFault |
BatName-FAILWrong battery brand selection What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| CAN FailFault |
CAN FailCAN Fail What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| OV-VbattFault |
OV-VbattBattery undervoltage detected What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| UN-VbattFault |
UN-VbattBattery overvoltage detected What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| Fan AlarmWarning |
Fan AlarmFan alarm What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| OV-DC01 (1020 DATA:0001)Fault |
OV-DC01 (1020 DATA:0001)DC 1 input overvoltage What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| OV-DC02 (1020 DATA:0002)Fault |
OV-DC02 (1020 DATA:0002)DC 2 input overvoltage What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| OV-BUS (1021 DATA:0000)Fault |
OV-BUS (1021 DATA:0000)DC bus overvoltage What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| UN-BUS01 (1023 DATA:0001)Fault |
UN-BUS01 (1023 DATA:0001)DC bus undervoltage What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| UNB-BUS (1022 DATA:0000)Warning |
UNB-BUS (1022 DATA:0000)DC bus unbalanced voltage What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| UN-BUS02 (1023 DATA:0002)Fault |
UN-BUS02 (1023 DATA:0002)Abnormal detection of DC bus voltage What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| DC-INTF. (1027 DATA:0000)Fault |
DC-INTF. (1027 DATA:0000)DC hardware overcurrent (1, 2, 3, 4) What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| OV-G-I (1018 DATA:0000)Fault |
OV-G-I (1018 DATA:0000)A phase RMS value overcurrent What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| OV-DCA-I (1025 DATA:0000)Fault |
OV-DCA-I (1025 DATA:0000)DC 1 average overcurrent What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| OV-DCB-I (1026 DATA:0000)Fault |
OV-DCB-I (1026 DATA:0000)DC 2 average overcurrent What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| GRID-INTF. (1030 DATA:0000)Fault |
GRID-INTF. (1030 DATA:0000)AC hardware overcurrent (abc phase) What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| DCInj-FAULT (1037 DATA:0000)Fault |
DCInj-FAULT (1037 DATA:0000)The current DC component exceeds the limit What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| IGBT-OV-I (1048 DATA:0000)Fault |
IGBT-OV-I (1048 DATA:0000)IGBT overcurrent What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| OV-TEM (1032 DATA:0000)Warning |
OV-TEM (1032 DATA:0000)Module over temperature What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| RelayChk-FAIL (1035 DATA:0000)Fault |
RelayChk-FAIL (1035 DATA:0000)Relay failure What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| UN-TEM (103A DATA:0000)Warning |
UN-TEM (103A DATA:0000)Low temperature protection What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| PV ISO-PRO01 (1033 DATA:0001)Safety-Critical |
PV ISO-PRO01 (1033 DATA:0001)PV negative ground fault What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| PV ISO-PRO02 (1033 DATA:0002)Safety-Critical |
PV ISO-PRO02 (1033 DATA:0002)PV positive ground fault What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| 12Power-FAULT (1038 DATA:0000)Fault |
12Power-FAULT (1038 DATA:0000)12V undervoltage failure What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| ILeak-PRO01 (1034 DATA:0001)Safety-Critical |
ILeak-PRO01 (1034 DATA:0001)Leakage current failure 01 (30mA) What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| ILeak-PRO02 (1034 DATA:0002)Safety-Critical |
ILeak-PRO02 (1034 DATA:0002)Leakage current failure 02 (60mA) What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| ILeak-PRO03 (1034 DATA:0003)Safety-Critical |
ILeak-PRO03 (1034 DATA:0003)Leakage current failure 03 (150mA) What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| ILeak-PRO04 (1034 DATA:0004)Safety-Critical |
ILeak-PRO04 (1034 DATA:0004)Leakage current failure 04 What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| ILeak_Check (1039 DATA:0000)Safety-Critical |
ILeak_Check (1039 DATA:0000)Leakage current sensor failure What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| GRID-INTF02 (1046 DATA:0000)Fault |
GRID-INTF02 (1046 DATA:0000)Power grid disturbance 02 What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| OV-Vbatt-H/ OV-BUS-H (1051 DATA:0000)Fault |
OV-Vbatt-H/ OV-BUS-H (1051 DATA:0000)Battery overvoltage hardware failure / VBUS What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| OV-ILLC (1052 DATA:0000)Fault |
OV-ILLC (1052 DATA:0000)LLC hardware overcurrent What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| INI-FAULT (1031 DATA:0000)Fault |
INI-FAULT (1031 DATA:0000)AD zero drift overlink What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| DSP-B-FAULT (1036 DATA:0000)Warning |
DSP-B-FAULT (1036 DATA:0000)The master-slave DSP communication is abnormal What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| AFCI-Check (1040 DATA:0000)Safety-Critical |
AFCI-Check (1040 DATA:0000)AFCI self-test failure What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
| ARC- FAULT (1041 DATA:0000)Safety-Critical |
ARC- FAULT (1041 DATA:0000)AFCI failure What you can do
S6-EH3P(5-10)K-H-AU three-phase hybrid · Guide only. All work must be done by a licensed electrician. |
No codes match. Try fewer characters, or ask us.
Common Solis questions
What does Solis Off "Off" mean?
Control device to shutdown Note the code, then restart the system once using the owner shutdown/start-up steps in your manual This is a guide only; any electrical work must be done by a licensed electrician.
What does Solis LmtByEPM "LmtByEPM" mean?
The device's output is under controlled Note the code, then restart the system once using the owner shutdown/start-up steps in your manual This is a guide only; any electrical work must be done by a licensed electrician.
What does Solis LmtByDRM "LmtByDRM" mean?
DRM Function ON Note the code, date and time and check the monitoring app This is a guide only; any electrical work must be done by a licensed electrician.
What does Solis LmtByVg "LmtByVg" mean?
The device is in the Volt-Watt mode Note the code, then restart the system once using the owner shutdown/start-up steps in your manual This is a guide only; any electrical work must be done by a licensed electrician.
What does Solis LmtByVar "LmtByVar" mean?
The device is in the Volt-Var mode of operation Note the code, then restart the system once using the owner shutdown/start-up steps in your manual This is a guide only; any electrical work must be done by a licensed electrician.
Need help with this fault?
Get a licensed electrician to call you back.
Total Solar can help: our licensed electricians install and service systems. Based in Ellenbrook, WA, with Victoria and Queensland also available.
Or call 1300 209 503
Sources
Meanings are summarised from these manufacturer documents. Check your own model's manual, as codes vary between models and firmware versions.
Solis is a trademark of its owner. Total Solar is not affiliated with the manufacturer unless stated. All fault code guides